deepasatwal200p8txnx deepasatwal200p8txnx
  • 16-05-2018
  • Mathematics
contestada

2 men and 5 women can do a piece of work in 4 days, while one man and one woman can finish it in 12 days. How long would it take for 1 man to do the work?

Respuesta :

Аноним Аноним
  • 16-05-2018
the answer is 12 days!
hope this helps!
Answer Link

Otras preguntas

Memory is defined as an active system that consists of three processes. they are ________.
PLEASE HELP SOON Prior to the French Revolution, which level of French society was taxed the most? a 1st Estate b 2nd Estate c 3rd Estate d 4th Estate
a square garden has a side of length that is 3 meters shorter than the length of a rectangle garden. Find the perimeter of the rectangle garden in terms of y. s
How has dollar diplomacy affected how countries behave in dealing with each other?
Correct these sentences. Lupe asked why doesnt he never do his homework
What is the rate at which goods and services are produced based upon total output given total inputs?
Sue held different part-time jobs during her summer holiday. The table below shows the total money she earned for different amounts of time, in hours: Hours Wor
Carlos solved the system of equations below. What mistake did he make in his work? 2x + y = 5 x − 2y = 10 y = 5 − 2x x − 2(5 − 2x) = 10 x + 10 + 4x = 10 5x + 10
Most likely, the elasticity of demand for transportation is greater than the elasticity of demand for cars. a. True b. False previous next
find the social security tax deducted for each weekly pay check of $237