Crashing almost always accelerates the schedule while increasing project risk, whereas fast tracking almost always accelerates the schedule while increasing project cost.A. TrueB. False

Respuesta :

gerald4764
gerald4764 gerald4764
  • 24-01-2020

Answer: False

Explanation: Because fast-tracking doesn’t involve additional resources, it’s usually best to start with this technique while Crashing requires careful planning to prevent “panic mode” among the project crews and to avoid acceleration claims.

Answer Link

Otras preguntas

any answers on this?
The cia was originally established at the end of _____.
The junior class of Eastlake High School has 146 students, and 67 of them are girls. How many boys are there in the class?
A rocket ship is travelling at an average speed of 1.75 Ă— 104 miles per hour. How many miles will the rocket ship travel in 1.2 Ă— 102 hours?1. Write the express
What is the value of 7 + z Ă· 2, when z = 10? Enter your answer in the box. WILL MARK BRAINLIEST
what is a common role played by animals in the carbon cycle ?
Use the discriminant to describe the roots of each equation. Then select the best description. 16x2 + 8x + 1 = 0 double root real and rational roots real and
What was the experience that mohamned had until a cave above mecca
explain when a relation is not a function?
Why was Charlemagne hesitant about being crowned Holy Roman Emperor