A project activity has an earliest completion time of 5, an activity time of 3, and a latest completion time of 6. What is the slack time for the activity?

Respuesta :

Tundexi
Tundexi Tundexi
  • 17-12-2020

Answer:

1

Explanation:

The Formula for calculating Slack Time is as below:

Slack Time = Latest Completion Time - Earliest Completion time

When Latest Completion Time = 6 ; Earliest Completion time = 5

Slack Time = 6 - 5

Slack Time = 1

Thus,  the slack time for the activity is 1 . The essence of calculating this is to prevent delays in the project completion.

Answer Link

Otras preguntas

You earn $35 for washing seven cars how much do uou earn for 4 cars
This is worth 15 points! Whoever gets this right gets brainlest.
Identify the classification to which this figure belongs . You must select all that apply
The Selective Service was designed to (5 points) a: create more rigorous requirements for men enlisting in the military b: raise money for the war effort throug
Classify each triangle by its angle and side :)
helpppppp find the x
Is this a scientific model? Use complete sentences to explain why or why not. (5 points) help quick
find the slope of the graph write it as a fraction or whole number not a mixed number. find two points on the line (0,-4) and (3,0) slope = change in y / chang
What is 2 2/3 divided by 1 1/2 ?
political movement of the industrial revolution ​