If 3 people can complete half of a job in 20 days, how long would it take for 12 people to do the complete job?

Respuesta :

queen0790
queen0790 queen0790
  • 17-02-2021

Answer:

If 3 people can complete half a job in 20 days, then three people can complete a job in 40 days. Since 12 people is four times as many, instead of taking 40 days, it should take 10 days

mark as brainlist

Answer Link

Otras preguntas

How did social organizations help African American communities
What is the solution of √1-3x=x+3
Which shows the first equation written in slope-intercept form?1/2 (2y + 10) = 7x​
2(n-1)+4n=2(3n-1)n=0no solutioninfinitely many solutions n= - 4HELP PLEASE!!!!!!!​
does the energy in a solid increase or decrease when changing to a liquid?
how would you prepare for unexpected expenses in a healthcare organization?
Which of the following is a third person plural pronoun
Question 13 (1 point) Jerome is starting a new job. His contract states he will earn $42,000 the first year, and will get a 4% raise per year. Which function S(
ASAP GUYS!!!! (I NEED TO FINISH THIS QUICK) Graph Complete the sequence of transformations that produces △X'Y'Z' from △XYZ. A clockwise rotation °______ about
What is the slope of the line passing through the points (3, 3) and (5, 7) ? 1. 2 2. 1/2 3. −2 4. −1/2