  • Mathematics
contestada

5 people cleared a plot of land in 15 days.How many people would i need to hire to clear three times that plot in 5 days​

Respuesta :

day1005
day1005 day1005
  • 18-07-2021

Answer:

45 people

Step-by-step explanation:

Answer Link
eilliyahrameen
eilliyahrameen eilliyahrameen
  • 18-07-2021

Answer:

45

Step-by-step explanation:

ln 15 days 5ppl work

ln 15 days if three times of that ppl work=5×3

=15ppl

So in 1 day=15×15\5 ppl

=45ppl

lt takes 45ppl to clear three times the plot in 5 days.

Answer Link

Otras preguntas

What are the organelles of a cone cell?
Name four behaviors that animals must use to survive
Name four behaviors that animals must use to survive
Caitlyn did 6/7 of the problems on her math correctly and 4 incorrectly. She did all the problems. How many were there?
What are the organelles of a cone cell?
Ned weighs 1.5 times as much as Jill and Tom weighs 15 kilograms more than Jill. If their combined weight is 190 kilograms, how much does each person weigh?
write a program in pascal to solve a quadratic equation
What are the organelles of a cone cell?
Caitlyn did 6/7 of the problems on her math correctly and 4 incorrectly. She did all the problems. How many were there?
Ned weighs 1.5 times as much as Jill and Tom weighs 15 kilograms more than Jill. If their combined weight is 190 kilograms, how much does each person weigh?