a company planned to finish a project with 80 people in 80 days.if after the initial 10 days,the number of people reduces to 70,by how many days will the project get delayed?​

Respuesta :

Аноним Аноним
  • 17-10-2021

Answer:

10 days delay

Step-by-step explanation:

in ten day 12.5% work done by 80 peoples

then 87.5% work hsas to be done by 70 peoples

the days consoder as 'x'

then( 70/x)*100 = 87.5

1/x = 87.5/7000

x =7000/87.5

x =80

so 70 peoples take 80 days to finish the work

so 10 days delay

Answer Link

Otras preguntas

1. A store in Grand Rapids, Michigan, advertised a side-by-side refrigerator for $1,699.99. a. What is the sales tax if the combined state and city rate is 6%?
The cost of a bag of fruits is proportional to the number of pounds. The cost for 1 ⅕ pound of fruit is $6.54. How much does a pound of fruits cost? Write an eq
Consider the substances quartz (SiOs), gold (Au), and nitrogen gas (N2). If possible, use the terms molecule and compound to describe each substance. If one or
Which three countries had the fewest immigrants come to the United States in 1880s? NO LINKS. NO DOWNLOADS. MAKE IT SO I CAN UNDERSTAND IT. 20 points.
What led to the Han golden age?
a)iii) as the wheelbarrow was being pushed, the tyre went over a small stone. Describe and explain how the pressure changes.​
Round each amount to the nearest hundred to find an estimate of: 9635 – 4891 A. 4400 B. 4500 C. 4600 D. 4700
when is a supplier standards form required to be provided to the beneficiary cvs
If f(x) = 1 - X, which value is equivalent to Ol? O o 1 2 V-1
two different isotopes of an element have different