A finishes a job in 10days,B finishes in 15days.if A and B work at it together, how many days will they take to complete the job​

Respuesta :

reinhard10158
reinhard10158 reinhard10158
  • 17-10-2021

Step-by-step explanation:

so, working together, in 1 day 1/10 + 1/15 of the work is done.

how many days (x) until we get 1/1 of the work done ?

x × (1/10 + 1/15) = 1

x × (3/30 + 2/30) = 1

x × 5/30 = 1

x×5 = 30

x = 30/5 = 6

so, together, they will finish the work in 6 days.

Answer Link

Otras preguntas

Las características individuales de una persona están determinadas, en gran parte, por ____
Throughout the play, Mrs. Peters reminds Mrs. Hale that "the law is the law" and "the law has got to punish crime." Why does Mrs. Peters likely believe this, an
Which BEST summarizes the narrator's key event? A) The narrator discovered her interest in history during a research assignment. B) The narrator discovered her
How would a drug that blocks acetylcholine release affect muscle contraction?
Ken is the new pastor at a local church. He is both nervous and excitedabout his new post and is looking forward to meeting all the members of his new congregat
A paragraph that talks about why you are not concerned about climate change
What’s the ratio hcl:h2o
A researcher is studying the effectiveness of an individualized evidence-based teaching plan on young women's intention to wear sunscreen to prevent skin cancer
How do I write x - y = 11 in slope-intercept form?
What is singular possessive, plural, and plural possessive of alumnus?