In a work breakdown structure, the sequence of tasks in which there is no slack is referred to as:

Respuesta :

Kalahira
Kalahira Kalahira
  • 25-10-2017
Critical path, the sequence of the tasks where there is no slack. Meaning if one task doesn't start on time because another has not yet been completed, there is no down time and there will inevitably be a delay in the project.
Answer Link

Otras preguntas

write an equation of the line in slope intercept form​
1. John is a runner. He runs the 200m sprint in 15s. What speed did he travel at? (in m/s).
Which sides of quadrilateral ABCD must be parallel? Explain. mZA= 54, mZB = 32, mZC = 148, mZD = 126
In which type of government does one person rule? I need it for a review for my US government class, it's due tomorrow!
On average, Christopher scores 2 goals in a soccer game but, depending on how well the opposing team is playing, his goal total can vary from the average by 1 g
What is 2000+90+70+60+4=
Which natural resource was most abundant in ancient Egypt? salt papyrus limestone sandstone
Which New England colony was established by the Separatists? O Massachusetts Bay O Rhode Island O Providence O Plymouth
1.Sixteen cyclists were each asked the number of miles they biked last week. Their responses are given below. You will be creating a frequency polygon of the da
A 200 kg object accelerate at a rate of 5.5m/s2. Calculate the force required to produce this acceleration.