If it takes 3 days for 10 workers to finish building one house, how many days will it take 15 workers to finish 4 houses?

Respuesta :

sirinda
sirinda sirinda
  • 19-10-2017
a = house
3 days x 10 worker = a
a = 30 work unit
4a = 120 work unit
120 work unit = 15 workers * y days
y = 120/15 = 8 days

i hope this isn't too confusing 
Answer Link

Otras preguntas

What is the verbal expression for 1/8y
Evaluate both successes and failures of faith based organizations
What was the first of two important changes that marked emperor constantine's rule?
Where in the windows registry would you store a key that starts an executable when the operating system starts?
Explain how the characters in prose narratives (myths, legends and folktales) of African traditional literature differ with regard to their character traits
Which statement in the press release is an example of bias? A. Volunteers are truly America's unsung heroes. B. Having a nationally recognized day gives ever
A city has a population of 300,000 people. suppose that each year the population grows by 5% . what will the population be after 9 years?
Banerjee Inc. wants to maintain a target capital structure with 30% debt and 70% equity. Its forecasted net income is $825,000, and its board of directors has d
Write the concentration equilibrium constant expression for this reaction. cr2o−27 (aq) + 6i− (aq) + 14h+ (aq) → 3i2 (s) + 2cr+3 (aq) + 7h2o (l)
The majority of the accessible drinking water on our planet comes from: