A network diagramming technique in which boxes represent activities is known as a(n) _____.

a. pdm

b. cpm

c. adm

d. pert

Respuesta :

StrongBad
StrongBad StrongBad
  • 16-11-2017
PERT is a review technique/tool, so that can't be it. CPM is Critical Path Method, and you can use a PDM or an ADM to chart it. 

The easy way to remember this answer, is that you write on the arrow when using the "arrow diagram method."  

So the answer is "a. pdm" (precedence diagram method).
Answer Link

Otras preguntas

help please pleaseeee​
14. What is the solution of the system? Use elimination. 9x + y = 30 6x - y = 15
How do you solve:(x-4)(x+2)=0
Judge the following sentence according to the criteria given below: Continental slopes around the margin of the Pacific Ocean are greater than the global averag
HELP WITH THIS, read carefully
John and Liz are sharing a large pizza. John ate 1/3 of the pizza, and Liz ate 1/4 of the pizza. How much of the pizza is left?
Which of the following is the equation for the graph shown? PLS HELP... NEED ANSWER ASAP
In what way is the English opium trade hypocritical?
How many moles of AlCl3 are in 2.25L of a 0.15 molar solution? A. 0.07 moles B. 0.15 moles C. 0.34 moles D. 15
Which of the following occurs as water vapor cools in the atmosphere? condensation transpiration precipitation evaporation